Building Progress

Enclosing with Walls and Windows

 Permanent link

The pre-cast walls are going up fast now and the windows are starting to go in. Work has also started on the roofing, insulation, storm sewers and even some interior plumbing. All of the pre-cast walls, with the exception of the entrances, should be up by the end of February.

 

These pictures were taken on February 13th and 20th, 2008.

New Building 20080213 001 New Building 20080220 001 New Building 20080220 002

Adding the Cafeteria

 Permanent link

With some of the pre-cast walls attached, they were able to work on adding the steel structure of the cafeteria.

 

These pictures were taken on January 30th, 2008.

New Building 20080130 001 New Building 20080130 002

Raising the Walls

 Permanent link

Work has begun on the pre-cast walls.  The pictures below show the south side of the building.

 

These pictures were taken on January 23rd, 2008.

New Building 20080123 001 New Building 20080123 002

Holiday Work

 Permanent link

Steel work, roofing and sanitary sewer lines continue to be worked on. Installing the pre-cast walls, which will enclose the entire building, is scheduled to begin the first full week in January.

 

These pictures were taken on December 19th, 2007.

New Building 20071219 001 New Building 20071219 002 New Building 20071219 003

Making progress

 Permanent link

Despite the weather we continue to make progress on the new building site. The entire concrete floor has been poured on second floor and half the roof has been installed. Over the next two weeks we will continue to install the second half of the roof and keep moving forward with the sanitary sewer lines and other utilities.

 

This picture was taken on December 5th, 2007.

New Building 20071205 001

Starting the plumbing

 Permanent link

The first picture shows the progress on pouring the concrete for the second floor.  They have one more section left to pour on the second floor.  In the second picture, they are starting to install the plumbing.

 

These pictures were taken on November 21st, 2007.

New Building 20071121 001 New Building 20071121 002

Pouring the Floor

 Permanent link

With the sub floor installed, they are now beginning to pour the concrete for the second floor.

 

These pictures were taken on November 7th, 2007.

New Building 20071107 001 New Building 20071107 002

Calendar

<< February 2008 >>
Sun Mon Tue Wed Thu Fri Sat
          1 2
3 4 5 6 7 8 9
10 11 12 13 14 15 16
17 18 19 20 21 22 23
24 25 26 27 28 29  

RSS Feed

RSS Feed

Archive