Work has begun on the pre-cast walls. The pictures below show the south side of the building.
These pictures were taken on January 23rd, 2008.
Steel work, roofing and sanitary sewer lines continue to be worked on. Installing the pre-cast walls, which will enclose the entire building, is scheduled to begin the first full week in January.
These pictures were taken on December 19th, 2007.
Despite the weather we continue to make progress on the new building site. The entire concrete floor has been poured on second floor and half the roof has been installed. Over the next two weeks we will continue to install the second half of the roof and keep moving forward with the sanitary sewer lines and other utilities.
This picture was taken on December 5th, 2007.
The first picture shows the progress on pouring the concrete for the second floor. They have one more section left to pour on the second floor. In the second picture, they are starting to install the plumbing.
These pictures were taken on November 21st, 2007.
With the sub floor installed, they are now beginning to pour the concrete for the second floor.
These pictures were taken on November 7th, 2007.
The rains earlier this month slowed construction down some, but the site has dried out well and work is back underway. The close-up picture shows the second floor sub floor prior to pouring concrete.
These pictures were taken on October 24th, 2007.
They continue to construct the steel frame and some of the roof trusses are starting to be set. You can also clearly see the elevator shaft in the center.
This is a view of the south side of the building, on October 3, 2007.